Rebuilding 3rd and 4th floor starts Tuesday 1 June 2021

6 May 2021

In June, the renovation of the workplaces of the Faculty Office (except SOLO and SSC) and the Institute CA-DS will start as part of the Activity-Oriented Housing (AOH) project.

Make an appointment via your planner to clear your workplace by 21 May 2021.

Time schedule for rebuilding

  • 25 May 2021: all items left behind are packed and stored.
    All items that are needed during the renovation period, that have no place on the faculty after the renovation or that are personal should be taken away. 
  • September 2021: Delivery of workstations Institute CA-DS
  • October 2021: Completion of workstations Faculty Office

Working on location remains possible

It will still be possible to work in the Pieter de la Court Building during the rebuilding period. Of course in accordance with the university corona guidelines. As usual, please make an appointment via your planner.

About AOH

The starting point of the project is a suitable workplace for every activity. Activity-oriented housing is necessary because the available space in our buildings can and must be used more efficiently. Pilots are the Institute CA-DS and the Faculty Office (except SOLO and SSC).