Upgrade wifi signal PdlC Building (incl. global planning)

21 June 2021

New Wi-Fi cabling will be installed during the summer months. This will improve the range and reliability of wifi connections throughout the PdlC building by 1 September 2021. Preparatory work is currently taking place, based on which the planning for the work in the halls and rooms will be made.

Global planning

FLOOR WORKS  PERIOD
6+7 Installation of cable ducts and cabling. Final assembly and testing.  14 - 26 June 2021
5 Dito 28 June - 17 July 2021
4 Dito 5 - 24 July 2021
3 Dito 12 - 31 July 2021
2 Dito 19 July - 7 August 2021
1 Dito 26 July - 14 August 2021
GF Dito 9 - 21 August 2021
Souterrain Dito 9 August - 4 September 2021
  Miscellaneous 30 August - 25 September 2021

Apologies for any inconvenience during the installation of the cable ducts.